23rd July’ 2007 |
The Government of Delhi decided to provide 1.5 Hectare of Land for setting up I.T.I. in this Area. |
08th April’ 2008 |
The Delhi Development Authority (DDA) allotted only 0.4 Hectare of Land. |
21st August’ 2008 |
Foundation stone laid. |
05th August’ 2013 |
Construction started withEstimated Cost Rs. 24.2 Crores. |
31st July’ 2015 |
The Construction work completed with the approximately cost ofexpenditure Rs. 15.9 Crores & the Net Saving is Rs. 8.3 Crores. |
04th August’ 2015 |
The institute starts its functioning with 10 Engineering & Non- Engineering Trades. |